Follow along with the progress of the barrier wall
As part of our commitment to our North Carolina neighbors, we want to keep the public informed on the progress being made at the Fayetteville plant to help improve the Cape Fear River.


UPDATE: February 22, 2022
Installation of the retaining walls along the Barrier Wall Road

UPDATE: February 22, 2022
Installation of GW Recovery Wells and Barrier Wall Road grading

UPDATE: March 3, 2022
ON THE RIGHT: Drilling the extraction wells; ON THE LEFT: Drilling to confirm the depth to the confining clay unit on the center line of barrier wall

UPDATE: April 8, 2022
Pad construction for the water treatment plant and installation of extraction well #55

UPDATE: April 8, 2022
Installation of the retaining walls along the barrier wall alignment

UPDATE: April 8, 2022
Installation of extraction wells in Willis Creek

UPDATE: April 12, 2022
Concrete pour of the first quadrant of the water treatment plant pad

UPDATE: April 22, 2022
Updated image of the Pad construction of the 004 water treatment plant

UPDATE: May 20, 2022
All GAC vessels delivered and, on the pad, as of this morning
We have begun and are currently in the final stages of developing the 90
percent design plan for submission to the NC Department of
Environmental Quality (DEQ).
The barrier wall is an integral part of our plan, and it will allow us to better capture the
groundwater so it can be treated before it is released in the river.

As civil work continues in preparation of the barrier wall construction, we
will continue to update you as we make progress on the planning and
future construction stages.
